Seamless Migrations. Safe Upgrades. No Downtime.

Migrating 10,000+ applications and upgrading 12,000 racks demanded careful execution. OpsWerks delivered — keeping production steady and delivery moving.

View PDF
Challenge

Legacy platform and aging hardware across 17 data centers had to be modernized without risking production outages.

Results
10,000+ apps migrated to a modern platform
12,000 racks upgraded across 17 data centers in 9 months
Zero unplanned service outages during migration and upgrades
60% app retirement reduced cost and fragility
20% faster builds and more reliable deployments
Impact

Smooth modernization at enterprise scale — no downtime, no disruption, predictable delivery.

Client Background

A Fortune 100 tech giant, home to one of the world’s largest developer ecosystems, faced mounting risk from aging infrastructure across its CI/CD platform and 17 data centers in the U.S. and around the world. Modernization was urgent to cut technical debt, improve reliability, and reduce costs. But it hinged on a large-scale migration and major updates — each carrying risk. The transition required methodical execution to prevent user disruption, protect mission-critical services, and sustain developer productivity.

The challenges

The modernization effort required two large-scale infrastructure transitions:

1

Platform migration

Our client needed to migrate more than 10,000 applications off a legacy, Heroku-style CI/CD platform built on Mesos onto a modern GitHub → Jenkins → Docker → Kubernetes toolchain.

Many apps were dormant or poorly maintained, leaving the platform brittle, inconsistent, and costly to operate.

Instability had turned builds into bottlenecks, slowing developer productivity and release velocity.

Migration was the only path forward but carried risks: downtime, broken dependencies, and disruption for thousands of developers.

2

Hardware upgrade

12,000 racks across 17 data centers required top-of-rack switch replacements, driven by a 9-month end-of-life (EOL) deadline and licensing constraints.

The challenge: execute this massive hardware upgrade with precision, managing global logistics and coordination.

At the same time, the team had to ensure zero disruption to production traffic or service availability.

Ops Werks' solution

Platform migration

At the outset, OpsWerks led a comprehensive discovery and classification effort across 10,000+ applications.

✔ Safely decommissioned ~60% of apps through automated reporting, spin-downs, and archiving.
✔ Retiring apps immediately cut resource consumption and operational overhead while reclaiming infrastructure.

For the remaining 40% of applications, OpsWerks provided white-glove migration support, combining precision planning, stakeholder coordination, and automation-driven execution.

To minimize friction and risk during the migration, the team:
✔ Built custom Dockerfiles to replicate legacy environments.
✔ Developed tailored build scripts and monitored cutovers for complex cases.
✔ Created runbooks and self-service guides.
✔ Automated backups so teams retained critical database data beyond standard retention windows.

This blend of automation and hands-on expertise streamlined the platform and enabled a smooth transition to the modern CI/CD toolchain.

Hardware upgrade

OpsWerks engineered a rack-by-rack execution strategy to modernize 12,000 racks across 17 data centers.

12,000
Racks Modernized
17
Data Centers
0
Service Impact

To safeguard the process and maintain efficiency, the team:

  • Developed a custom Python health validation framework for pre- and post-upgrade checks.
  • Built real-time dashboards to track upgrade status and completion.
  • Automated Slack alerts and scheduled cutovers aligned with production freeze windows.
  • Orchestrated cross-datacenter logistics, including rack-by-rack scheduling, to keep upgrades consistent and predictable.
These measures ensured 12,000 racks were upgraded on schedule with no service disruption — modernizing the network backbone while maintaining business continuity.
 

Scope of work

  • Application migration: Audited 10,000+ applications, decommissioned 60%, and migrated 40% to a modern GitHub → Jenkins → Docker → Kubernetes delivery platform.
  • Data center upgrade: Engineered automation and orchestration frameworks that enabled safe rack-by-rack top-of-rack switch replacements across 12,000 racks in 17 data centers.
  • Global coordination: Managed logistics and cutovers across the U.S. and around the world, aligned with production freeze windows.
  • Timeline: Delivered both modernization initiatives under a hard 9-month end-of-life deadline — with zero downtime.

Results

20% faster build times

and more reliable deployments.

60% of apps retired

reducing fragility and operating cost.

12,000 racks upgraded

in 17 data centers in just 9 months.

Zero service outages

during migration and upgrades.

Modernized DevOps pipeline

increasing stability, velocity, and release cycles.

Created repeatable playbook

for large-scale migrations with zero impact.

I really want to thank you for digging me and the rest of us out of this particular hole. It was very appreciated. I'm very happy with you guys.

– Engineering Director

Facing Similar
Challenges?

Contact our Partner Success Team at partnerwithus@opswerks.com to see how we can help. Or book a meeting directly with us below.

OpsWerks success cup

About OpsWerks

OpsWerks is a trusted partner to the world's most elite platform and infrastructure engineering teams, helping them operate at scale.

We streamline hybrid cloud operations, execute complex migrations without downtime, and enable developers to quickly build and deploy global apps used by hundreds of millions.

From managing CI/CD ecosystems and building orchestration tools to 24/7 support for business-critical systems, for over a decade we’ve kept developers focused on building.